Bimonthly Progress Report on PMSSY projects of more than Rs. 10 crore with CPWD



Project 1

Up gradation of Govt. Medical College & Hospital under Phase-III of PMSSY at Akola Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room


Zone WZ II
Approved DPR cost(AA & ES) 52.00(Amount in Rs crore )
Approved contract value 48.00
Date of Award / Target date of completion 10.09.2016 / 09.01.2018
Date of completion as per current progress 31.10.2020
Status of work work is in progress. Civil work is 99.5% complete and Electrical work 99.5% complete. Overall work is 99.5% complete.
Amount allocated 55.35(Amount in Rs crore )
Hindrances
  1. During 1st week of November, 2017 the representative of M/s HITES ( HLL Infratech services Ltd ) Noida Inspected the ongoing construction works and suggested following major changes.
  2. Increase of 5th floor height from 3.90 m to 4.70 m since Modular Operation Theatres (MOTs) has to be installed in this floor. The concept of Modular OTs was not under scope of original scope of work of agreement. This resulted in changes of floor height and change in sizes of OTs in fifth floor. Providing ad
Completion chart

Project 2

Construction of Superspeciality Hospital at Patliputra Medical College, Dhanbad under PMSSY Phase-III


Zone EZ IV
Approved DPR cost(AA & ES) 857100.00(Amount in Rs crore )
Approved contract value 500800.00
Date of Award / Target date of completion 27.08.2016 / 26.12.2017
Date of completion as per current progress 26.12.2017
Status of work Block-A 1st & 2nd floor roof slab has been casted. Block-B 1st floor roof slab has been casted and column work is in progress for casting of 2nd floor reinforcement binding work is in progress. Block
Amount allocated 220700.00(Amount in Rs crore )
Hindrances

Initially, the site was hindered by the local public & heavy Rainfall causing delays in foundation work.Also the approach of the site was totally blocked by Durga puja committee during the puja festival ( 2 months).

Completion chart

Project 3

Upgradation of SVN Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal.


Zone
Approved DPR cost(AA & ES) 74.36(Amount in Rs crore )
Approved contract value 48.47
Date of Award / Target date of completion 12.09.2016 / 31.10.2019
Date of completion as per current progress 11.01.2018
Status of work Work is in progress and 83% completed.
Amount allocated 58.00(Amount in Rs crore )
Hindrances

Agency submitted proposal for rescheduling of milestones. Comments / Clarifications sought by EE from agency - yet to be received.

Completion chart

Project 4

Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum


Zone
Approved DPR cost(AA & ES) 150.00(Amount in Rs crore )
Approved contract value 44.00
Date of Award / Target date of completion 12.02.2018 / 31.03.2020
Date of completion as per current progress 29.08.2019
Status of work Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuttering in progress
Amount allocated 69.00(Amount in Rs crore )
Hindrances

Initial delay in handing over site & finalisation of drawings

Completion chart

Project 5

Up-gradation of Jawahar Lal Nehru Medical College & Hospital, Bhagalpur under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.


Zone REGION
Approved DPR cost(AA & ES) 109.00(Amount in Rs crore )
Approved contract value 101.00
Date of Award / Target date of completion 17.07.2018 / 16.02.2020
Date of completion as per current progress 30.03.2023
Status of work Completed . Testing & commissioning of Civil & E&M services are being checked. Minor touch up work is going on in tune with HITES work.
Amount allocated 103.00(Amount in Rs crore )
Hindrances

Work was delayed due to 2nd call of tender. The first call of tender was done on 14.12.2017 and 2nd call on 14.05.2018. The conceptual drawing was approved on 07/12/2018. Non-receipt of statutory approval up to 02/2019. Work also slowed down during Lok Sabha General Election 2019 due to non-availability/scarcity of materials. Excessive rainfall and water logging at the site in June, and July 2019. First-floor Slab casting stopped due to unprecedented rain and water logging in the last week of

Completion chart

Project 6

Up gradation of Shri Vasantrao Naik Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room


Zone WZ II
Approved DPR cost(AA & ES) 52.00(Amount in Rs crore )
Approved contract value 48.00
Date of Award / Target date of completion 12.09.2016 / 11.01.2018
Date of completion as per current progress 30.11.2020
Status of work Works are in progress. Civil work is 99% complete and Electrical work is 85% complete. Overall work is 97% complete.
Amount allocated 58.00(Amount in Rs crore )
Hindrances
  1. Delay due to existing LT/HT poles passing through the location of Hospital Building.
  2. Delay due to existing water supply line passing the foundation of Middle Wing of Building.
  3. Revision of floor drawings after the inspection of HITES in November 2017 and final drawing issued on 16th January 2018. Major issue was to increase the height of 5th floor height from 3.9 m to 4.7 m and various additional requirements.
  4. Delay in taking up the UG sump & Substation building due to existing W/S
Completion chart

Project 7

Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum


Zone
Approved DPR cost(AA & ES) 150.00(Amount in Rs crore )
Approved contract value 44.00
Date of Award / Target date of completion 12.02.2018 / 31.03.2020
Date of completion as per current progress 29.08.2019
Status of work Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuttering in progress.
Amount allocated 69.00(Amount in Rs crore )
Hindrances

Initial delay in handing over site & finalization of drawings.

Completion chart

Project 8

C/o super specialty Hospital, Bilaspur under PMSSY phase IV on EPC


Zone REGION
Approved DPR cost(AA & ES) 109.00(Amount in Rs crore )
Approved contract value 98.62
Date of Award / Target date of completion 09.08.2018 / 08.05.2020
Date of completion as per current progress 23.02.2021
Status of work 1) RCC frame structure up to seventh Floor slab,50% 8th floor slab is completed. 2)Brick work up to 5th floor, service building first floor column, ug tank raft foundation, ramp, road work is going on.
Amount allocated 64.21(Amount in Rs crore )
Hindrances
  1. There is an initial delay due to the shifting of the site location.
  2. Delay in the demarcation of land by the state government officials due to which the Process of obtaining different statuary Approvals was delayed.
  3. Due to the delay in the execution of work as client department demands a full basement instead of the basement in 25 % of the area as mentioned in the agreement.
  4. Due to the delay in the basement, foundation work fell in the rainy season and backfilling works were delayed as backfilling soil was not available due to the rainy day.
Completion chart

Project 9

C/O AIIMS AT AWANTIPORA (KASHMIR) (J&K)


Zone CE CUM ED(AIIMS AWANTIPURA)
Approved DPR cost(AA & ES) 15770000000.00(Amount in Rs crore )
Approved contract value 16493752000.00
Date of Award / Target date of completion 07.11.2020 / 22.05.2024
Date of completion as per current progress 22.05.2024
Status of work Work has been awarded with stipulated date of start and completion as 23.11.2020 and 22.05.2024 respectively (Period of construction 42 Months).The Contractor (M/s NCC Ltd) has started mobilization o
Amount allocated 420000000.00(Amount in Rs crore )
Hindrances

Expeditious completion of utilities by state government (Road, Water, Electricity), Multiple point access to site, Allotment of balance 34 acre land, Security for construction at site are required to take up the project in a time bound manner. Also, deposition of funds by MoHFW is required immediately.

Completion chart

Project 10

Upgradation of Patna Medical College and Hospital , Patna under PMSSY (Phase-IV)


Zone CE(PATNA)
Approved DPR cost(AA & ES) 118.00(Amount in Rs crore )
Approved contract value 84.00
Date of Award / Target date of completion 07.03.2019 / 30.11.2021
Date of completion as per current progress 06.11.2020
Status of work Foundation work in progress.
Amount allocated 36.00(Amount in Rs crore )
Hindrances

Non-handing over of hindrance free site, Local body submission and approval got delayed due to non-availability of land records, Land possession certificate not yet received, Delay in receipt of EIA clearance, Land for multilevel parking not yet handed over. Delay due to Cobid pandemic.

Completion chart

Project 11

UP-GRADATION OF PATNA MEDICAL COLLEGE & HOSPITAL UNDER PMSSY, PHASE-IV


Zone CE(PATNA)
Approved DPR cost(AA & ES) 119.00(Amount in Rs crore )
Approved contract value 85.00
Date of Award / Target date of completion 07.03.2019 / 31.05.2022
Date of completion as per current progress 06.11.2020
Status of work 1. Initial Pile Load test Completed. 2. Shifting of tree and transformer completed. 3. Land Document (Land Possession Certificate) yet not received from PMCH, Patna, The land record and detail of due
Amount allocated 36.00(Amount in Rs crore )
Hindrances
  1. Tender Invited on 18.12.2017(first call) and due to unavailability of land tender was cancelled on 03.04.2018 after extending the date of opening four times.
  2. The tender re-invited on 18.07.2018 with stipulated date of opening on 09.08.2018.
  3. Award of work got delayed by 5 months due to delay in handing over of land by PMCH on 13.02.2019 vide letter no 824.
  4. The delay in vacation old structure/quarter at site of main Building.
  5. Central dispensary yet to be vacated/demolished.
Completion chart

Project 12

Up-gradation of Anugrah Narayan Magadh Medical College & Hospital, Gaya under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.


Zone CE CUM ED(BODHGAYA PROJECT ZONE)
Approved DPR cost(AA & ES) 108.00(Amount in Rs crore )
Approved contract value 90.32
Date of Award / Target date of completion 13.04.2018 / 30.09.2020
Date of completion as per current progress 24.04.2020
Status of work i.)Service Block:- Structural Work Completed. Brick & Plaster Work was in Progress. ii) Main Building :- Terrace Level Casting was in progress. Brick & Plaster work was in Progress.
Amount allocated 47.11(Amount in Rs crore )
Hindrances

Due to the following reasons, the work has been delayed:( A). Initial Hindrance for Starting the Work Smoothly:-

  1. Due to the land document not hand over by ANMMCH, the Planning, and finalization of the Layout was delayed.
  2. Due to the conceptual drawing not being approved by the Ministry of Health and Family Welfare, the Planning and finalization of the Layout was delayed.
  3. Due to the pending NOC for Dismantling of Qtrs and Hostel from Building Construction Deptt, Gaya, foundation work was delayed.
  4. Due to pending shifting of Overhead
Completion chart

Project 13

Upgradation of IGIMS Patna under PMSSY (Phase-VB)


Zone CE(PATNA)
Approved DPR cost(AA & ES) 119.00(Amount in Rs crore )
Approved contract value 80.00
Date of Award / Target date of completion 22.11.2020 / 21.05.2022
Date of completion as per current progress 28.05.2022
Status of work EPC Contract, Planning work in progress, All input on architectural drawings received from client on 13-01-2021, Approval of Structure DBR conveyed, Approval of
Amount allocated 12.00(Amount in Rs crore )
Hindrances

Environmental Clearance is in process, next meeting of SEAC likely in mid february 2021.

Completion chart

Project 14

CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT BILASPUR UNDER PMSSY (PHASE-IV)


Zone REGION
Approved DPR cost(AA & ES) 109.00(Amount in Rs crore )
Approved contract value 86.00
Date of Award / Target date of completion 31.08.2018 / 31.12.2022
Date of completion as per current progress 30.04.2020
Status of work Civil: - 92.25% Electrical: -75% Hospital Building (Basement +G+10) Storied- Flooring 96%completed (except basement), B/W, internal Plaster, Sanitary pipeline, Internal Water supply line-96% com
Amount allocated 90.00(Amount in Rs crore )
Hindrances
  1. There is an initial delay due to the shifting of the site location.
  2. Delay in the demarcation of land, P2 form, nazri naksha nakal naksha by the state government officials due to which the Process of obtaining different statuary Approvals was delayed.
  3. Due to the delay in the execution of work as client department demands a full basement instead of the basement in 25 % of the area as mentioned in the agreement.
  4. Due to the delay in the basement, foundation work falls in the rainy season and backfilling works are delayed as backfilling.
Completion chart

Project 15

Up-gradation of Agartala Government Medical College, Tripura under PMSSY Phase-III at Agartala. [Sub Head: Construction of Super Specialty Block to house 07 Super specialty facilities with 170 beds including internal & external water supply, sanitary installations, drainage, electrical installations, air-conditioning, development etc.


Zone
Approved DPR cost(AA & ES) 1145400000.00(Amount in Rs crore )
Approved contract value 1145400000.00
Date of Award / Target date of completion 29.03.2017 / 14.10.2019
Date of completion as per current progress 14.10.2019
Status of work 1. Site Clearance, plant and machinery set up in progress. Barricading with GI sheet in from of building has been completed.2. Pile test design & retaining wall design submitted by the contractor. Des
Amount allocated 100000000.00(Amount in Rs crore )
Hindrances

There is no delay as of now for design activities. However, There are few unauthorized hutments within the site of construction. Matter has been taken up with state authorities for their removal.

Completion chart

Project 16

CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT PATLIPUTRA MEDICAL COLLEGE UNDER PMSSY PHASE-III AT DHANBAD, JHARKHAND


Zone EZ IV
Approved DPR cost(AA & ES) 85.71(Amount in Rs crore )
Approved contract value 50.08
Date of Award / Target date of completion 15.07.2016 / 26.12.2017
Date of completion as per current progress 14.01.2018
Status of work Physical Progress-37%.Block-A-2nd floor slab has been casted, 3rd floor column work is in progress. Block-B 1st floor casted & reinforcement binding work is in progress. Block-C 3rd floor roof slab cast
Amount allocated 22.07(Amount in Rs crore )
Hindrances

Initially work start delayed due to heavy rain fall and subsequent flooding of work site being a slopy terrain.

Completion chart

Project 17

Upgradation of Baba Raghav Das Medical College at Gorakhpur under PMSSY Phase-3.


Zone
Approved DPR cost(AA & ES) 69.87(Amount in Rs crore )
Approved contract value 43.97
Date of Award / Target date of completion 19.05.2016 / 18.10.2017
Date of completion as per current progress 31.01.2018
Status of work RCC works in progress for terrace slab, brickwork in progress at GF, 1st Floor & 2nd floor. Achieved ducting & Fire Fighting material arrived at site. Targets Physical -55% Achieved 52%, Financial 47% Achieved.
Amount allocated 29.00(Amount in Rs crore )
Hindrances

Initial delay of 3 months in removal of encroachment from site by the college. Some encroachment still exists at rear side road location. Limited availability of sand & aggregates in UP.

Completion chart

Project 18

Upgradation of Lala Lajpat Rai Memorial Medical College at Meerut under PMSSY Phase-3.


Zone NZ II
Approved DPR cost(AA & ES) 69.99(Amount in Rs crore )
Approved contract value 47.49
Date of Award / Target date of completion 11.06.2016 / 10.11.2017
Date of completion as per current progress 10.11.2017
Status of work RCC work up to terrace and brick work completed.Plastering, tiling work, HVAC & fire fighting work in progress. Cumulative targets Physical-74% Achieved-66% Financial-59% Achieved-55%
Amount allocated 24.98(Amount in Rs crore )
Hindrances

Progress (Activities like RCC, brickwork, plastering etc) got slowed down during April to Middle of June due to non-availability of sand/aggregates in U.P

Completion chart

Project 19

Trauma Centre and Emergency Medical Block at Malda Medical College and Hospital at Malda under PMSSY Phase-3.


Zone EZ I
Approved DPR cost(AA & ES) 61.39(Amount in Rs crore )
Approved contract value 44.96
Date of Award / Target date of completion 17.12.2016 / 16.08.2018
Date of completion as per current progress 31.12.2018
Status of work The work is yet to start as site has not been made available by the hospital administration.
Amount allocated 6.13(Amount in Rs crore )
Hindrances

Site not clear. Nurses hostel existing on the site is being demolished by the college.

Completion chart

Project 20

Up-gradation of B. S. Medical College, Bankura under PMSSY, Phase-III


Zone EZ III
Approved DPR cost(AA & ES) 79.00(Amount in Rs crore )
Approved contract value 54.50
Date of Award / Target date of completion 05.08.2016 / 31.03.2018
Date of completion as per current progress 31.03.2018
Status of work Shuttering of 4th slab in progress.
Amount allocated 41.00(Amount in Rs crore )
Hindrances
  1. Site handed over by the Client on 05.09.2016 while the stipulated date of start is 20.08.2016.
  2. Exact locations of medical equipments not received from HITES so far
Completion chart

Project 21

Upgradation of Government Medical College & Hospital at Akola under PMSSY Phase-3.


Zone
Approved DPR cost(AA & ES) 74.75(Amount in Rs crore )
Approved contract value 48.19
Date of Award / Target date of completion 10.09.2016 / 31.10.2019
Date of completion as per current progress 09.01.2018
Status of work Right block-1st floor slab & beam reinforcement placing in progress. Left block- 3rd floor columns in progress. AAC block masonry completed at GF. Work is 96% completed
Amount allocated 48.00(Amount in Rs crore )
Hindrances

1st & 2nd Milestones shifted by 75 days. The agency agreed to cover up this delay of 75 days by the end of 3rd milestone. Hence the date target date is the same as the stipulated date of completion.

Completion chart

Project 1

Up gradation of Govt. Medical College & Hospital under Phase-III of PMSSY at Akola Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room


Zone WZ II
Approved DPR cost(AA & ES) 52.00(Amount in Rs crore )
Approved contract value 48.00
Date of Award / Target date of completion 10.09.2016 / 09.01.2018
Date of completion as per current progress 31.10.2020
Status of work work is in progress. Civil work is 99.5% complete and Electrical work 99.5% complete. Overall work is 99.5% complete.
Amount allocated 55.35(Amount in Rs crore )
Hindrances
  1. During 1st week of November, 2017 the representative of M/s HITES ( HLL Infratech services Ltd ) Noida Inspected the ongoing construction works and suggested following major changes.
  2. Increase of 5th floor height from 3.90 m to 4.70 m since Modular Operation Theatres (MOTs) has to be installed in this floor. The concept of Modular OTs was not under scope of original scope of work of agreement. This resulted in changes of floor height and change in sizes of OTs in fifth floor. Providing ad
Completion chart

Project 2

Construction of Superspeciality Hospital at Patliputra Medical College, Dhanbad under PMSSY Phase-III


Zone EZ IV
Approved DPR cost(AA & ES) 857100.00(Amount in Rs crore )
Approved contract value 500800.00
Date of Award / Target date of completion 27.08.2016 / 26.12.2017
Date of completion as per current progress 26.12.2017
Status of work Block-A 1st & 2nd floor roof slab has been casted. Block-B 1st floor roof slab has been casted and column work is in progress for casting of 2nd floor reinforcement binding work is in progress. Block
Amount allocated 220700.00(Amount in Rs crore )
Hindrances

Initially, the site was hindered by the local public & heavy Rainfall causing delays in foundation work.Also the approach of the site was totally blocked by Durga puja committee during the puja festival ( 2 months).

Completion chart

Project 3

Upgradation of SVN Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal.


Zone
Approved DPR cost(AA & ES) 74.36(Amount in Rs crore )
Approved contract value 48.47
Date of Award / Target date of completion 12.09.2016 / 31.10.2019
Date of completion as per current progress 11.01.2018
Status of work Work is in progress and 83% completed.
Amount allocated 58.00(Amount in Rs crore )
Hindrances

Agency submitted proposal for rescheduling of milestones. Comments / Clarifications sought by EE from agency - yet to be received.

Completion chart

Project 4

Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum


Zone
Approved DPR cost(AA & ES) 150.00(Amount in Rs crore )
Approved contract value 44.00
Date of Award / Target date of completion 12.02.2018 / 31.03.2020
Date of completion as per current progress 29.08.2019
Status of work Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuttering in progress
Amount allocated 69.00(Amount in Rs crore )
Hindrances

Initial delay in handing over site & finalisation of drawings

Completion chart

Project 5

Up-gradation of Jawahar Lal Nehru Medical College & Hospital, Bhagalpur under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.


Zone REGION
Approved DPR cost(AA & ES) 109.00(Amount in Rs crore )
Approved contract value 101.00
Date of Award / Target date of completion 17.07.2018 / 16.02.2020
Date of completion as per current progress 30.03.2023
Status of work Completed . Testing & commissioning of Civil & E&M services are being checked. Minor touch up work is going on in tune with HITES work.
Amount allocated 103.00(Amount in Rs crore )
Hindrances

Work was delayed due to 2nd call of tender. The first call of tender was done on 14.12.2017 and 2nd call on 14.05.2018. The conceptual drawing was approved on 07/12/2018. Non-receipt of statutory approval up to 02/2019. Work also slowed down during Lok Sabha General Election 2019 due to non-availability/scarcity of materials. Excessive rainfall and water logging at the site in June, and July 2019. First-floor Slab casting stopped due to unprecedented rain and water logging in the last week of

Completion chart

Project 6

Up gradation of Shri Vasantrao Naik Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room


Zone WZ II
Approved DPR cost(AA & ES) 52.00(Amount in Rs crore )
Approved contract value 48.00
Date of Award / Target date of completion 12.09.2016 / 11.01.2018
Date of completion as per current progress 30.11.2020
Status of work Works are in progress. Civil work is 99% complete and Electrical work is 85% complete. Overall work is 97% complete.
Amount allocated 58.00(Amount in Rs crore )
Hindrances
  1. Delay due to existing LT/HT poles passing through the location of Hospital Building.
  2. Delay due to existing water supply line passing the foundation of Middle Wing of Building.
  3. Revision of floor drawings after the inspection of HITES in November 2017 and final drawing issued on 16th January 2018. Major issue was to increase the height of 5th floor height from 3.9 m to 4.7 m and various additional requirements.
  4. Delay in taking up the UG sump & Substation building due to existing W/S
Completion chart

Project 7

Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum


Zone
Approved DPR cost(AA & ES) 150.00(Amount in Rs crore )
Approved contract value 44.00
Date of Award / Target date of completion 12.02.2018 / 31.03.2020
Date of completion as per current progress 29.08.2019
Status of work Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuttering in progress.
Amount allocated 69.00(Amount in Rs crore )
Hindrances

Initial delay in handing over site & finalization of drawings.

Completion chart

Project 8

C/o super specialty Hospital, Bilaspur under PMSSY phase IV on EPC


Zone REGION
Approved DPR cost(AA & ES) 109.00(Amount in Rs crore )
Approved contract value 98.62
Date of Award / Target date of completion 09.08.2018 / 08.05.2020
Date of completion as per current progress 23.02.2021
Status of work 1) RCC frame structure up to seventh Floor slab,50% 8th floor slab is completed. 2)Brick work up to 5th floor, service building first floor column, ug tank raft foundation, ramp, road work is going on.
Amount allocated 64.21(Amount in Rs crore )
Hindrances
  1. There is an initial delay due to the shifting of the site location.
  2. Delay in the demarcation of land by the state government officials due to which the Process of obtaining different statuary Approvals was delayed.
  3. Due to the delay in the execution of work as client department demands a full basement instead of the basement in 25 % of the area as mentioned in the agreement.
  4. Due to the delay in the basement, foundation work fell in the rainy season and backfilling works were delayed as backfilling soil was not available due to the rainy day.
Completion chart

Project 9

C/O AIIMS AT AWANTIPORA (KASHMIR) (J&K)


Zone CE CUM ED(AIIMS AWANTIPURA)
Approved DPR cost(AA & ES) 15770000000.00(Amount in Rs crore )
Approved contract value 16493752000.00
Date of Award / Target date of completion 07.11.2020 / 22.05.2024
Date of completion as per current progress 22.05.2024
Status of work Work has been awarded with stipulated date of start and completion as 23.11.2020 and 22.05.2024 respectively (Period of construction 42 Months).The Contractor (M/s NCC Ltd) has started mobilization o
Amount allocated 420000000.00(Amount in Rs crore )
Hindrances

Expeditious completion of utilities by state government (Road, Water, Electricity), Multiple point access to site, Allotment of balance 34 acre land, Security for construction at site are required to take up the project in a time bound manner. Also, deposition of funds by MoHFW is required immediately.

Completion chart

Project 10

Upgradation of Patna Medical College and Hospital , Patna under PMSSY (Phase-IV)


Zone CE(PATNA)
Approved DPR cost(AA & ES) 118.00(Amount in Rs crore )
Approved contract value 84.00
Date of Award / Target date of completion 07.03.2019 / 30.11.2021
Date of completion as per current progress 06.11.2020
Status of work Foundation work in progress.
Amount allocated 36.00(Amount in Rs crore )
Hindrances

Non-handing over of hindrance free site, Local body submission and approval got delayed due to non-availability of land records, Land possession certificate not yet received, Delay in receipt of EIA clearance, Land for multilevel parking not yet handed over. Delay due to Cobid pandemic.

Completion chart

Project 11

UP-GRADATION OF PATNA MEDICAL COLLEGE & HOSPITAL UNDER PMSSY, PHASE-IV


Zone CE(PATNA)
Approved DPR cost(AA & ES) 119.00(Amount in Rs crore )
Approved contract value 85.00
Date of Award / Target date of completion 07.03.2019 / 31.05.2022
Date of completion as per current progress 06.11.2020
Status of work 1. Initial Pile Load test Completed. 2. Shifting of tree and transformer completed. 3. Land Document (Land Possession Certificate) yet not received from PMCH, Patna, The land record and detail of due
Amount allocated 36.00(Amount in Rs crore )
Hindrances
  1. Tender Invited on 18.12.2017(first call) and due to unavailability of land tender was cancelled on 03.04.2018 after extending the date of opening four times.
  2. The tender re-invited on 18.07.2018 with stipulated date of opening on 09.08.2018.
  3. Award of work got delayed by 5 months due to delay in handing over of land by PMCH on 13.02.2019 vide letter no 824.
  4. The delay in vacation old structure/quarter at site of main Building.
  5. Central dispensary yet to be vacated/demolished.
Completion chart

Project 12

Up-gradation of Anugrah Narayan Magadh Medical College & Hospital, Gaya under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.


Zone CE CUM ED(BODHGAYA PROJECT ZONE)
Approved DPR cost(AA & ES) 108.00(Amount in Rs crore )
Approved contract value 90.32
Date of Award / Target date of completion 13.04.2018 / 30.09.2020
Date of completion as per current progress 24.04.2020
Status of work i.)Service Block:- Structural Work Completed. Brick & Plaster Work was in Progress. ii) Main Building :- Terrace Level Casting was in progress. Brick & Plaster work was in Progress.
Amount allocated 47.11(Amount in Rs crore )
Hindrances

Due to the following reasons, the work has been delayed:( A). Initial Hindrance for Starting the Work Smoothly:-

  1. Due to the land document not hand over by ANMMCH, the Planning, and finalization of the Layout was delayed.
  2. Due to the conceptual drawing not being approved by the Ministry of Health and Family Welfare, the Planning and finalization of the Layout was delayed.
  3. Due to the pending NOC for Dismantling of Qtrs and Hostel from Building Construction Deptt, Gaya, foundation work was delayed.
  4. Due to pending shifting of Overhead
Completion chart

Project 13

Upgradation of IGIMS Patna under PMSSY (Phase-VB)


Zone CE(PATNA)
Approved DPR cost(AA & ES) 119.00(Amount in Rs crore )
Approved contract value 80.00
Date of Award / Target date of completion 22.11.2020 / 21.05.2022
Date of completion as per current progress 28.05.2022
Status of work EPC Contract, Planning work in progress, All input on architectural drawings received from client on 13-01-2021, Approval of Structure DBR conveyed, Approval of
Amount allocated 12.00(Amount in Rs crore )
Hindrances

Environmental Clearance is in process, next meeting of SEAC likely in mid february 2021.

Completion chart

Project 14

CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT BILASPUR UNDER PMSSY (PHASE-IV)


Zone REGION
Approved DPR cost(AA & ES) 109.00(Amount in Rs crore )
Approved contract value 86.00
Date of Award / Target date of completion 31.08.2018 / 31.12.2022
Date of completion as per current progress 30.04.2020
Status of work Civil: - 92.25% Electrical: -75% Hospital Building (Basement +G+10) Storied- Flooring 96%completed (except basement), B/W, internal Plaster, Sanitary pipeline, Internal Water supply line-96% com
Amount allocated 90.00(Amount in Rs crore )
Hindrances
  1. There is an initial delay due to the shifting of the site location.
  2. Delay in the demarcation of land, P2 form, nazri naksha nakal naksha by the state government officials due to which the Process of obtaining different statuary Approvals was delayed.
  3. Due to the delay in the execution of work as client department demands a full basement instead of the basement in 25 % of the area as mentioned in the agreement.
  4. Due to the delay in the basement, foundation work falls in the rainy season and backfilling works are delayed as backfilling.
Completion chart

Project 15

Up-gradation of Agartala Government Medical College, Tripura under PMSSY Phase-III at Agartala. [Sub Head: Construction of Super Specialty Block to house 07 Super specialty facilities with 170 beds including internal & external water supply, sanitary installations, drainage, electrical installations, air-conditioning, development etc.


Zone
Approved DPR cost(AA & ES) 1145400000.00(Amount in Rs crore )
Approved contract value 1145400000.00
Date of Award / Target date of completion 29.03.2017 / 14.10.2019
Date of completion as per current progress 14.10.2019
Status of work 1. Site Clearance, plant and machinery set up in progress. Barricading with GI sheet in from of building has been completed.2. Pile test design & retaining wall design submitted by the contractor. Des
Amount allocated 100000000.00(Amount in Rs crore )
Hindrances

There is no delay as of now for design activities. However, There are few unauthorized hutments within the site of construction. Matter has been taken up with state authorities for their removal.

Completion chart

Project 16

CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT PATLIPUTRA MEDICAL COLLEGE UNDER PMSSY PHASE-III AT DHANBAD, JHARKHAND


Zone EZ IV
Approved DPR cost(AA & ES) 85.71(Amount in Rs crore )
Approved contract value 50.08
Date of Award / Target date of completion 15.07.2016 / 26.12.2017
Date of completion as per current progress 14.01.2018
Status of work Physical Progress-37%.Block-A-2nd floor slab has been casted, 3rd floor column work is in progress. Block-B 1st floor casted & reinforcement binding work is in progress. Block-C 3rd floor roof slab cast
Amount allocated 22.07(Amount in Rs crore )
Hindrances

Initially work start delayed due to heavy rain fall and subsequent flooding of work site being a slopy terrain.

Completion chart

Project 17

Upgradation of Baba Raghav Das Medical College at Gorakhpur under PMSSY Phase-3.


Zone
Approved DPR cost(AA & ES) 69.87(Amount in Rs crore )
Approved contract value 43.97
Date of Award / Target date of completion 19.05.2016 / 18.10.2017
Date of completion as per current progress 31.01.2018
Status of work RCC works in progress for terrace slab, brickwork in progress at GF, 1st Floor & 2nd floor. Achieved ducting & Fire Fighting material arrived at site. Targets Physical -55% Achieved 52%, Financial 47% Achieved.
Amount allocated 29.00(Amount in Rs crore )
Hindrances

Initial delay of 3 months in removal of encroachment from site by the college. Some encroachment still exists at rear side road location. Limited availability of sand & aggregates in UP.

Completion chart

Project 18

Upgradation of Lala Lajpat Rai Memorial Medical College at Meerut under PMSSY Phase-3.


Zone NZ II
Approved DPR cost(AA & ES) 69.99(Amount in Rs crore )
Approved contract value 47.49
Date of Award / Target date of completion 11.06.2016 / 10.11.2017
Date of completion as per current progress 10.11.2017
Status of work RCC work up to terrace and brick work completed.Plastering, tiling work, HVAC & fire fighting work in progress. Cumulative targets Physical-74% Achieved-66% Financial-59% Achieved-55%
Amount allocated 24.98(Amount in Rs crore )
Hindrances

Progress (Activities like RCC, brickwork, plastering etc) got slowed down during April to Middle of June due to non-availability of sand/aggregates in U.P

Completion chart

Project 19

Trauma Centre and Emergency Medical Block at Malda Medical College and Hospital at Malda under PMSSY Phase-3.


Zone EZ I
Approved DPR cost(AA & ES) 61.39(Amount in Rs crore )
Approved contract value 44.96
Date of Award / Target date of completion 17.12.2016 / 16.08.2018
Date of completion as per current progress 31.12.2018
Status of work The work is yet to start as site has not been made available by the hospital administration.
Amount allocated 6.13(Amount in Rs crore )
Hindrances

Site not clear. Nurses hostel existing on the site is being demolished by the college.

Completion chart

Project 20

Up-gradation of B. S. Medical College, Bankura under PMSSY, Phase-III


Zone EZ III
Approved DPR cost(AA & ES) 79.00(Amount in Rs crore )
Approved contract value 54.50
Date of Award / Target date of completion 05.08.2016 / 31.03.2018
Date of completion as per current progress 31.03.2018
Status of work Shuttering of 4th slab in progress.
Amount allocated 41.00(Amount in Rs crore )
Hindrances
  1. Site handed over by the Client on 05.09.2016 while the stipulated date of start is 20.08.2016.
  2. Exact locations of medical equipments not received from HITES so far
Completion chart

Project 21

Upgradation of Government Medical College & Hospital at Akola under PMSSY Phase-3.


Zone
Approved DPR cost(AA & ES) 74.75(Amount in Rs crore )
Approved contract value 48.19
Date of Award / Target date of completion 10.09.2016 / 31.10.2019
Date of completion as per current progress 09.01.2018
Status of work Right block-1st floor slab & beam reinforcement placing in progress. Left block- 3rd floor columns in progress. AAC block masonry completed at GF. Work is 96% completed
Amount allocated 48.00(Amount in Rs crore )
Hindrances

1st & 2nd Milestones shifted by 75 days. The agency agreed to cover up this delay of 75 days by the end of 3rd milestone. Hence the date target date is the same as the stipulated date of completion.

Completion chart