Health Infrastructure Projects - CPWD
Bimonthly Progress Report on PMSSY projects of more than Rs. 10 crore with CPWD
Project 1
Up gradation of Govt. Medical College & Hospital under Phase-III of PMSSY at Akola Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room
| Zone | WZ II |
|---|---|
| Approved DPR cost(AA & ES) | 52.00(Amount in Rs crore ) |
| Approved contract value | 48.00 |
| Date of Award / Target date of completion | 10.09.2016 / 09.01.2018 |
| Date of completion as per current progress | 31.10.2020 |
| Status of work | work is in progress. Civil work is 99.5% complete and Electrical work 99.5% complete. Overall work is 99.5% complete. |
| Amount allocated | 55.35(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 2
Construction of Superspeciality Hospital at Patliputra Medical College, Dhanbad under PMSSY Phase-III
| Zone | EZ IV |
|---|---|
| Approved DPR cost(AA & ES) | 857100.00(Amount in Rs crore ) |
| Approved contract value | 500800.00 |
| Date of Award / Target date of completion | 27.08.2016 / 26.12.2017 |
| Date of completion as per current progress | 26.12.2017 |
| Status of work | Block-A 1st & 2nd floor roof slab has been casted. Block-B 1st floor roof slab has been casted and column work is in progress for casting of 2nd floor reinforcement binding work is in progress. Block |
| Amount allocated | 220700.00(Amount in Rs crore ) |
| Hindrances | Initially, the site was hindered by the local public & heavy Rainfall causing delays in foundation work.Also the approach of the site was totally blocked by Durga puja committee during the puja festival ( 2 months). |
| Completion chart |
Project 3
Upgradation of SVN Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal.
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 74.36(Amount in Rs crore ) |
| Approved contract value | 48.47 |
| Date of Award / Target date of completion | 12.09.2016 / 31.10.2019 |
| Date of completion as per current progress | 11.01.2018 |
| Status of work | Work is in progress and 83% completed. |
| Amount allocated | 58.00(Amount in Rs crore ) |
| Hindrances | Agency submitted proposal for rescheduling of milestones. Comments / Clarifications sought by EE from agency - yet to be received. |
| Completion chart |
Project 4
Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 150.00(Amount in Rs crore ) |
| Approved contract value | 44.00 |
| Date of Award / Target date of completion | 12.02.2018 / 31.03.2020 |
| Date of completion as per current progress | 29.08.2019 |
| Status of work | Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuttering in progress |
| Amount allocated | 69.00(Amount in Rs crore ) |
| Hindrances | Initial delay in handing over site & finalisation of drawings |
| Completion chart |
Project 5
Up-gradation of Jawahar Lal Nehru Medical College & Hospital, Bhagalpur under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.
| Zone | REGION |
|---|---|
| Approved DPR cost(AA & ES) | 109.00(Amount in Rs crore ) |
| Approved contract value | 101.00 |
| Date of Award / Target date of completion | 17.07.2018 / 16.02.2020 |
| Date of completion as per current progress | 30.03.2023 |
| Status of work | Completed . Testing & commissioning of Civil & E&M services are being checked. Minor touch up work is going on in tune with HITES work. |
| Amount allocated | 103.00(Amount in Rs crore ) |
| Hindrances | Work was delayed due to 2nd call of tender. The first call of tender was done on 14.12.2017 and 2nd call on 14.05.2018. The conceptual drawing was approved on 07/12/2018. Non-receipt of statutory approval up to 02/2019. Work also slowed down during Lok Sabha General Election 2019 due to non-availability/scarcity of materials. Excessive rainfall and water logging at the site in June, and July 2019. First-floor Slab casting stopped due to unprecedented rain and water logging in the last week of |
| Completion chart |
Project 6
Up gradation of Shri Vasantrao Naik Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room
| Zone | WZ II |
|---|---|
| Approved DPR cost(AA & ES) | 52.00(Amount in Rs crore ) |
| Approved contract value | 48.00 |
| Date of Award / Target date of completion | 12.09.2016 / 11.01.2018 |
| Date of completion as per current progress | 30.11.2020 |
| Status of work | Works are in progress. Civil work is 99% complete and Electrical work is 85% complete. Overall work is 97% complete. |
| Amount allocated | 58.00(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 7
Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 150.00(Amount in Rs crore ) |
| Approved contract value | 44.00 |
| Date of Award / Target date of completion | 12.02.2018 / 31.03.2020 |
| Date of completion as per current progress | 29.08.2019 |
| Status of work | Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuttering in progress. |
| Amount allocated | 69.00(Amount in Rs crore ) |
| Hindrances | Initial delay in handing over site & finalization of drawings. |
| Completion chart |
Project 8
C/o super specialty Hospital, Bilaspur under PMSSY phase IV on EPC
| Zone | REGION |
|---|---|
| Approved DPR cost(AA & ES) | 109.00(Amount in Rs crore ) |
| Approved contract value | 98.62 |
| Date of Award / Target date of completion | 09.08.2018 / 08.05.2020 |
| Date of completion as per current progress | 23.02.2021 |
| Status of work | 1) RCC frame structure up to seventh Floor slab,50% 8th floor slab is completed. 2)Brick work up to 5th floor, service building first floor column, ug tank raft foundation, ramp, road work is going on. |
| Amount allocated | 64.21(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 9
C/O AIIMS AT AWANTIPORA (KASHMIR) (J&K)
| Zone | CE CUM ED(AIIMS AWANTIPURA) |
|---|---|
| Approved DPR cost(AA & ES) | 15770000000.00(Amount in Rs crore ) |
| Approved contract value | 16493752000.00 |
| Date of Award / Target date of completion | 07.11.2020 / 22.05.2024 |
| Date of completion as per current progress | 22.05.2024 |
| Status of work | Work has been awarded with stipulated date of start and completion as 23.11.2020 and 22.05.2024 respectively (Period of construction 42 Months).The Contractor (M/s NCC Ltd) has started mobilization o |
| Amount allocated | 420000000.00(Amount in Rs crore ) |
| Hindrances | Expeditious completion of utilities by state government (Road, Water, Electricity), Multiple point access to site, Allotment of balance 34 acre land, Security for construction at site are required to take up the project in a time bound manner. Also, deposition of funds by MoHFW is required immediately. |
| Completion chart |
Project 10
Upgradation of Patna Medical College and Hospital , Patna under PMSSY (Phase-IV)
| Zone | CE(PATNA) |
|---|---|
| Approved DPR cost(AA & ES) | 118.00(Amount in Rs crore ) |
| Approved contract value | 84.00 |
| Date of Award / Target date of completion | 07.03.2019 / 30.11.2021 |
| Date of completion as per current progress | 06.11.2020 |
| Status of work | Foundation work in progress. |
| Amount allocated | 36.00(Amount in Rs crore ) |
| Hindrances | Non-handing over of hindrance free site, Local body submission and approval got delayed due to non-availability of land records, Land possession certificate not yet received, Delay in receipt of EIA clearance, Land for multilevel parking not yet handed over. Delay due to Cobid pandemic. |
| Completion chart |
Project 11
UP-GRADATION OF PATNA MEDICAL COLLEGE & HOSPITAL UNDER PMSSY, PHASE-IV
| Zone | CE(PATNA) |
|---|---|
| Approved DPR cost(AA & ES) | 119.00(Amount in Rs crore ) |
| Approved contract value | 85.00 |
| Date of Award / Target date of completion | 07.03.2019 / 31.05.2022 |
| Date of completion as per current progress | 06.11.2020 |
| Status of work | 1. Initial Pile Load test Completed. 2. Shifting of tree and transformer completed. 3. Land Document (Land Possession Certificate) yet not received from PMCH, Patna, The land record and detail of due |
| Amount allocated | 36.00(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 12
Up-gradation of Anugrah Narayan Magadh Medical College & Hospital, Gaya under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.
| Zone | CE CUM ED(BODHGAYA PROJECT ZONE) |
|---|---|
| Approved DPR cost(AA & ES) | 108.00(Amount in Rs crore ) |
| Approved contract value | 90.32 |
| Date of Award / Target date of completion | 13.04.2018 / 30.09.2020 |
| Date of completion as per current progress | 24.04.2020 |
| Status of work | i.)Service Block:- Structural Work Completed. Brick & Plaster Work was in Progress. ii) Main Building :- Terrace Level Casting was in progress. Brick & Plaster work was in Progress. |
| Amount allocated | 47.11(Amount in Rs crore ) |
| Hindrances | Due to the following reasons, the work has been delayed:( A). Initial Hindrance for Starting the Work Smoothly:-
|
| Completion chart |
Project 13
Upgradation of IGIMS Patna under PMSSY (Phase-VB)
| Zone | CE(PATNA) |
|---|---|
| Approved DPR cost(AA & ES) | 119.00(Amount in Rs crore ) |
| Approved contract value | 80.00 |
| Date of Award / Target date of completion | 22.11.2020 / 21.05.2022 |
| Date of completion as per current progress | 28.05.2022 |
| Status of work | EPC Contract, Planning work in progress, All input on architectural drawings received from client on 13-01-2021, Approval of Structure DBR conveyed, Approval of |
| Amount allocated | 12.00(Amount in Rs crore ) |
| Hindrances | Environmental Clearance is in process, next meeting of SEAC likely in mid february 2021. |
| Completion chart |
Project 14
CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT BILASPUR UNDER PMSSY (PHASE-IV)
| Zone | REGION |
|---|---|
| Approved DPR cost(AA & ES) | 109.00(Amount in Rs crore ) |
| Approved contract value | 86.00 |
| Date of Award / Target date of completion | 31.08.2018 / 31.12.2022 |
| Date of completion as per current progress | 30.04.2020 |
| Status of work | Civil: - 92.25% Electrical: -75% Hospital Building (Basement +G+10) Storied- Flooring 96%completed (except basement), B/W, internal Plaster, Sanitary pipeline, Internal Water supply line-96% com |
| Amount allocated | 90.00(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 15
Up-gradation of Agartala Government Medical College, Tripura under PMSSY Phase-III at Agartala. [Sub Head: Construction of Super Specialty Block to house 07 Super specialty facilities with 170 beds including internal & external water supply, sanitary installations, drainage, electrical installations, air-conditioning, development etc.
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 1145400000.00(Amount in Rs crore ) |
| Approved contract value | 1145400000.00 |
| Date of Award / Target date of completion | 29.03.2017 / 14.10.2019 |
| Date of completion as per current progress | 14.10.2019 |
| Status of work | 1. Site Clearance, plant and machinery set up in progress. Barricading with GI sheet in from of building has been completed.2. Pile test design & retaining wall design submitted by the contractor. Des |
| Amount allocated | 100000000.00(Amount in Rs crore ) |
| Hindrances | There is no delay as of now for design activities. However, There are few unauthorized hutments within the site of construction. Matter has been taken up with state authorities for their removal. |
| Completion chart |
Project 16
CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT PATLIPUTRA MEDICAL COLLEGE UNDER PMSSY PHASE-III AT DHANBAD, JHARKHAND
| Zone | EZ IV |
|---|---|
| Approved DPR cost(AA & ES) | 85.71(Amount in Rs crore ) |
| Approved contract value | 50.08 |
| Date of Award / Target date of completion | 15.07.2016 / 26.12.2017 |
| Date of completion as per current progress | 14.01.2018 |
| Status of work | Physical Progress-37%.Block-A-2nd floor slab has been casted, 3rd floor column work is in progress. Block-B 1st floor casted & reinforcement binding work is in progress. Block-C 3rd floor roof slab cast |
| Amount allocated | 22.07(Amount in Rs crore ) |
| Hindrances | Initially work start delayed due to heavy rain fall and subsequent flooding of work site being a slopy terrain. |
| Completion chart |
Project 17
Upgradation of Baba Raghav Das Medical College at Gorakhpur under PMSSY Phase-3.
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 69.87(Amount in Rs crore ) |
| Approved contract value | 43.97 |
| Date of Award / Target date of completion | 19.05.2016 / 18.10.2017 |
| Date of completion as per current progress | 31.01.2018 |
| Status of work | RCC works in progress for terrace slab, brickwork in progress at GF, 1st Floor & 2nd floor. Achieved ducting & Fire Fighting material arrived at site. Targets Physical -55% Achieved 52%, Financial 47% Achieved. |
| Amount allocated | 29.00(Amount in Rs crore ) |
| Hindrances | Initial delay of 3 months in removal of encroachment from site by the college. Some encroachment still exists at rear side road location. Limited availability of sand & aggregates in UP. |
| Completion chart |
Project 18
Upgradation of Lala Lajpat Rai Memorial Medical College at Meerut under PMSSY Phase-3.
| Zone | NZ II |
|---|---|
| Approved DPR cost(AA & ES) | 69.99(Amount in Rs crore ) |
| Approved contract value | 47.49 |
| Date of Award / Target date of completion | 11.06.2016 / 10.11.2017 |
| Date of completion as per current progress | 10.11.2017 |
| Status of work | RCC work up to terrace and brick work completed.Plastering, tiling work, HVAC & fire fighting work in progress. Cumulative targets Physical-74% Achieved-66% Financial-59% Achieved-55% |
| Amount allocated | 24.98(Amount in Rs crore ) |
| Hindrances | Progress (Activities like RCC, brickwork, plastering etc) got slowed down during April to Middle of June due to non-availability of sand/aggregates in U.P |
| Completion chart |
Project 19
Trauma Centre and Emergency Medical Block at Malda Medical College and Hospital at Malda under PMSSY Phase-3.
| Zone | EZ I |
|---|---|
| Approved DPR cost(AA & ES) | 61.39(Amount in Rs crore ) |
| Approved contract value | 44.96 |
| Date of Award / Target date of completion | 17.12.2016 / 16.08.2018 |
| Date of completion as per current progress | 31.12.2018 |
| Status of work | The work is yet to start as site has not been made available by the hospital administration. |
| Amount allocated | 6.13(Amount in Rs crore ) |
| Hindrances | Site not clear. Nurses hostel existing on the site is being demolished by the college. |
| Completion chart |
Project 20
Up-gradation of B. S. Medical College, Bankura under PMSSY, Phase-III
| Zone | EZ III |
|---|---|
| Approved DPR cost(AA & ES) | 79.00(Amount in Rs crore ) |
| Approved contract value | 54.50 |
| Date of Award / Target date of completion | 05.08.2016 / 31.03.2018 |
| Date of completion as per current progress | 31.03.2018 |
| Status of work | Shuttering of 4th slab in progress. |
| Amount allocated | 41.00(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 21
Upgradation of Government Medical College & Hospital at Akola under PMSSY Phase-3.
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 74.75(Amount in Rs crore ) |
| Approved contract value | 48.19 |
| Date of Award / Target date of completion | 10.09.2016 / 31.10.2019 |
| Date of completion as per current progress | 09.01.2018 |
| Status of work | Right block-1st floor slab & beam reinforcement placing in progress. Left block- 3rd floor columns in progress. AAC block masonry completed at GF. Work is 96% completed |
| Amount allocated | 48.00(Amount in Rs crore ) |
| Hindrances | 1st & 2nd Milestones shifted by 75 days. The agency agreed to cover up this delay of 75 days by the end of 3rd milestone. Hence the date target date is the same as the stipulated date of completion. |
| Completion chart |
Project 1
Up gradation of Govt. Medical College & Hospital under Phase-III of PMSSY at Akola Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room
| Zone | WZ II |
|---|---|
| Approved DPR cost(AA & ES) | 52.00(Amount in Rs crore ) |
| Approved contract value | 48.00 |
| Date of Award / Target date of completion | 10.09.2016 / 09.01.2018 |
| Date of completion as per current progress | 31.10.2020 |
| Status of work | work is in progress. Civil work is 99.5% complete and Electrical work 99.5% complete. Overall work is 99.5% complete. |
| Amount allocated | 55.35(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 2
Construction of Superspeciality Hospital at Patliputra Medical College, Dhanbad under PMSSY Phase-III
| Zone | EZ IV |
|---|---|
| Approved DPR cost(AA & ES) | 857100.00(Amount in Rs crore ) |
| Approved contract value | 500800.00 |
| Date of Award / Target date of completion | 27.08.2016 / 26.12.2017 |
| Date of completion as per current progress | 26.12.2017 |
| Status of work | Block-A 1st & 2nd floor roof slab has been casted. Block-B 1st floor roof slab has been casted and column work is in progress for casting of 2nd floor reinforcement binding work is in progress. Block |
| Amount allocated | 220700.00(Amount in Rs crore ) |
| Hindrances | Initially, the site was hindered by the local public & heavy Rainfall causing delays in foundation work.Also the approach of the site was totally blocked by Durga puja committee during the puja festival ( 2 months). |
| Completion chart |
Project 3
Upgradation of SVN Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal.
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 74.36(Amount in Rs crore ) |
| Approved contract value | 48.47 |
| Date of Award / Target date of completion | 12.09.2016 / 31.10.2019 |
| Date of completion as per current progress | 11.01.2018 |
| Status of work | Work is in progress and 83% completed. |
| Amount allocated | 58.00(Amount in Rs crore ) |
| Hindrances | Agency submitted proposal for rescheduling of milestones. Comments / Clarifications sought by EE from agency - yet to be received. |
| Completion chart |
Project 4
Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 150.00(Amount in Rs crore ) |
| Approved contract value | 44.00 |
| Date of Award / Target date of completion | 12.02.2018 / 31.03.2020 |
| Date of completion as per current progress | 29.08.2019 |
| Status of work | Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuttering in progress |
| Amount allocated | 69.00(Amount in Rs crore ) |
| Hindrances | Initial delay in handing over site & finalisation of drawings |
| Completion chart |
Project 5
Up-gradation of Jawahar Lal Nehru Medical College & Hospital, Bhagalpur under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.
| Zone | REGION |
|---|---|
| Approved DPR cost(AA & ES) | 109.00(Amount in Rs crore ) |
| Approved contract value | 101.00 |
| Date of Award / Target date of completion | 17.07.2018 / 16.02.2020 |
| Date of completion as per current progress | 30.03.2023 |
| Status of work | Completed . Testing & commissioning of Civil & E&M services are being checked. Minor touch up work is going on in tune with HITES work. |
| Amount allocated | 103.00(Amount in Rs crore ) |
| Hindrances | Work was delayed due to 2nd call of tender. The first call of tender was done on 14.12.2017 and 2nd call on 14.05.2018. The conceptual drawing was approved on 07/12/2018. Non-receipt of statutory approval up to 02/2019. Work also slowed down during Lok Sabha General Election 2019 due to non-availability/scarcity of materials. Excessive rainfall and water logging at the site in June, and July 2019. First-floor Slab casting stopped due to unprecedented rain and water logging in the last week of |
| Completion chart |
Project 6
Up gradation of Shri Vasantrao Naik Govt. Medical College & Hospital under Phase-III of PMSSY at Yavatmal Maharashtra SH: Construction of Super specialty Block including internal Roads, UG Sump, STP Electric sub Station etc. Including E/M Works like EI & Fans, Sub Station equipment, DG Set, FAS, FF, UPS Water supply pumps, CCTV, PA, Lifts, HVAC, BMS, STP, LAN, EPABX, Street Light Singages & AV System in Seminar Room
| Zone | WZ II |
|---|---|
| Approved DPR cost(AA & ES) | 52.00(Amount in Rs crore ) |
| Approved contract value | 48.00 |
| Date of Award / Target date of completion | 12.09.2016 / 11.01.2018 |
| Date of completion as per current progress | 30.11.2020 |
| Status of work | Works are in progress. Civil work is 99% complete and Electrical work is 85% complete. Overall work is 97% complete. |
| Amount allocated | 58.00(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 7
Construction of New Hospital Block for Sree Chitra Thirunal Institute for Medical Sciences and Technology, Medical College Campus, Trivandrum
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 150.00(Amount in Rs crore ) |
| Approved contract value | 44.00 |
| Date of Award / Target date of completion | 12.02.2018 / 31.03.2020 |
| Date of completion as per current progress | 29.08.2019 |
| Status of work | Package 1 for RCC structure: F4 slb nearing completion. F5 slab right wing shuttering in progress. |
| Amount allocated | 69.00(Amount in Rs crore ) |
| Hindrances | Initial delay in handing over site & finalization of drawings. |
| Completion chart |
Project 8
C/o super specialty Hospital, Bilaspur under PMSSY phase IV on EPC
| Zone | REGION |
|---|---|
| Approved DPR cost(AA & ES) | 109.00(Amount in Rs crore ) |
| Approved contract value | 98.62 |
| Date of Award / Target date of completion | 09.08.2018 / 08.05.2020 |
| Date of completion as per current progress | 23.02.2021 |
| Status of work | 1) RCC frame structure up to seventh Floor slab,50% 8th floor slab is completed. 2)Brick work up to 5th floor, service building first floor column, ug tank raft foundation, ramp, road work is going on. |
| Amount allocated | 64.21(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 9
C/O AIIMS AT AWANTIPORA (KASHMIR) (J&K)
| Zone | CE CUM ED(AIIMS AWANTIPURA) |
|---|---|
| Approved DPR cost(AA & ES) | 15770000000.00(Amount in Rs crore ) |
| Approved contract value | 16493752000.00 |
| Date of Award / Target date of completion | 07.11.2020 / 22.05.2024 |
| Date of completion as per current progress | 22.05.2024 |
| Status of work | Work has been awarded with stipulated date of start and completion as 23.11.2020 and 22.05.2024 respectively (Period of construction 42 Months).The Contractor (M/s NCC Ltd) has started mobilization o |
| Amount allocated | 420000000.00(Amount in Rs crore ) |
| Hindrances | Expeditious completion of utilities by state government (Road, Water, Electricity), Multiple point access to site, Allotment of balance 34 acre land, Security for construction at site are required to take up the project in a time bound manner. Also, deposition of funds by MoHFW is required immediately. |
| Completion chart |
Project 10
Upgradation of Patna Medical College and Hospital , Patna under PMSSY (Phase-IV)
| Zone | CE(PATNA) |
|---|---|
| Approved DPR cost(AA & ES) | 118.00(Amount in Rs crore ) |
| Approved contract value | 84.00 |
| Date of Award / Target date of completion | 07.03.2019 / 30.11.2021 |
| Date of completion as per current progress | 06.11.2020 |
| Status of work | Foundation work in progress. |
| Amount allocated | 36.00(Amount in Rs crore ) |
| Hindrances | Non-handing over of hindrance free site, Local body submission and approval got delayed due to non-availability of land records, Land possession certificate not yet received, Delay in receipt of EIA clearance, Land for multilevel parking not yet handed over. Delay due to Cobid pandemic. |
| Completion chart |
Project 11
UP-GRADATION OF PATNA MEDICAL COLLEGE & HOSPITAL UNDER PMSSY, PHASE-IV
| Zone | CE(PATNA) |
|---|---|
| Approved DPR cost(AA & ES) | 119.00(Amount in Rs crore ) |
| Approved contract value | 85.00 |
| Date of Award / Target date of completion | 07.03.2019 / 31.05.2022 |
| Date of completion as per current progress | 06.11.2020 |
| Status of work | 1. Initial Pile Load test Completed. 2. Shifting of tree and transformer completed. 3. Land Document (Land Possession Certificate) yet not received from PMCH, Patna, The land record and detail of due |
| Amount allocated | 36.00(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 12
Up-gradation of Anugrah Narayan Magadh Medical College & Hospital, Gaya under PMSSY (Phase-IV) on Engineering, Procurement and Construction (EPC) basis.
| Zone | CE CUM ED(BODHGAYA PROJECT ZONE) |
|---|---|
| Approved DPR cost(AA & ES) | 108.00(Amount in Rs crore ) |
| Approved contract value | 90.32 |
| Date of Award / Target date of completion | 13.04.2018 / 30.09.2020 |
| Date of completion as per current progress | 24.04.2020 |
| Status of work | i.)Service Block:- Structural Work Completed. Brick & Plaster Work was in Progress. ii) Main Building :- Terrace Level Casting was in progress. Brick & Plaster work was in Progress. |
| Amount allocated | 47.11(Amount in Rs crore ) |
| Hindrances | Due to the following reasons, the work has been delayed:( A). Initial Hindrance for Starting the Work Smoothly:-
|
| Completion chart |
Project 13
Upgradation of IGIMS Patna under PMSSY (Phase-VB)
| Zone | CE(PATNA) |
|---|---|
| Approved DPR cost(AA & ES) | 119.00(Amount in Rs crore ) |
| Approved contract value | 80.00 |
| Date of Award / Target date of completion | 22.11.2020 / 21.05.2022 |
| Date of completion as per current progress | 28.05.2022 |
| Status of work | EPC Contract, Planning work in progress, All input on architectural drawings received from client on 13-01-2021, Approval of Structure DBR conveyed, Approval of |
| Amount allocated | 12.00(Amount in Rs crore ) |
| Hindrances | Environmental Clearance is in process, next meeting of SEAC likely in mid february 2021. |
| Completion chart |
Project 14
CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT BILASPUR UNDER PMSSY (PHASE-IV)
| Zone | REGION |
|---|---|
| Approved DPR cost(AA & ES) | 109.00(Amount in Rs crore ) |
| Approved contract value | 86.00 |
| Date of Award / Target date of completion | 31.08.2018 / 31.12.2022 |
| Date of completion as per current progress | 30.04.2020 |
| Status of work | Civil: - 92.25% Electrical: -75% Hospital Building (Basement +G+10) Storied- Flooring 96%completed (except basement), B/W, internal Plaster, Sanitary pipeline, Internal Water supply line-96% com |
| Amount allocated | 90.00(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 15
Up-gradation of Agartala Government Medical College, Tripura under PMSSY Phase-III at Agartala. [Sub Head: Construction of Super Specialty Block to house 07 Super specialty facilities with 170 beds including internal & external water supply, sanitary installations, drainage, electrical installations, air-conditioning, development etc.
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 1145400000.00(Amount in Rs crore ) |
| Approved contract value | 1145400000.00 |
| Date of Award / Target date of completion | 29.03.2017 / 14.10.2019 |
| Date of completion as per current progress | 14.10.2019 |
| Status of work | 1. Site Clearance, plant and machinery set up in progress. Barricading with GI sheet in from of building has been completed.2. Pile test design & retaining wall design submitted by the contractor. Des |
| Amount allocated | 100000000.00(Amount in Rs crore ) |
| Hindrances | There is no delay as of now for design activities. However, There are few unauthorized hutments within the site of construction. Matter has been taken up with state authorities for their removal. |
| Completion chart |
Project 16
CONSTRUCTION OF SUPER SPECIALTY HOSPITAL AT PATLIPUTRA MEDICAL COLLEGE UNDER PMSSY PHASE-III AT DHANBAD, JHARKHAND
| Zone | EZ IV |
|---|---|
| Approved DPR cost(AA & ES) | 85.71(Amount in Rs crore ) |
| Approved contract value | 50.08 |
| Date of Award / Target date of completion | 15.07.2016 / 26.12.2017 |
| Date of completion as per current progress | 14.01.2018 |
| Status of work | Physical Progress-37%.Block-A-2nd floor slab has been casted, 3rd floor column work is in progress. Block-B 1st floor casted & reinforcement binding work is in progress. Block-C 3rd floor roof slab cast |
| Amount allocated | 22.07(Amount in Rs crore ) |
| Hindrances | Initially work start delayed due to heavy rain fall and subsequent flooding of work site being a slopy terrain. |
| Completion chart |
Project 17
Upgradation of Baba Raghav Das Medical College at Gorakhpur under PMSSY Phase-3.
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 69.87(Amount in Rs crore ) |
| Approved contract value | 43.97 |
| Date of Award / Target date of completion | 19.05.2016 / 18.10.2017 |
| Date of completion as per current progress | 31.01.2018 |
| Status of work | RCC works in progress for terrace slab, brickwork in progress at GF, 1st Floor & 2nd floor. Achieved ducting & Fire Fighting material arrived at site. Targets Physical -55% Achieved 52%, Financial 47% Achieved. |
| Amount allocated | 29.00(Amount in Rs crore ) |
| Hindrances | Initial delay of 3 months in removal of encroachment from site by the college. Some encroachment still exists at rear side road location. Limited availability of sand & aggregates in UP. |
| Completion chart |
Project 18
Upgradation of Lala Lajpat Rai Memorial Medical College at Meerut under PMSSY Phase-3.
| Zone | NZ II |
|---|---|
| Approved DPR cost(AA & ES) | 69.99(Amount in Rs crore ) |
| Approved contract value | 47.49 |
| Date of Award / Target date of completion | 11.06.2016 / 10.11.2017 |
| Date of completion as per current progress | 10.11.2017 |
| Status of work | RCC work up to terrace and brick work completed.Plastering, tiling work, HVAC & fire fighting work in progress. Cumulative targets Physical-74% Achieved-66% Financial-59% Achieved-55% |
| Amount allocated | 24.98(Amount in Rs crore ) |
| Hindrances | Progress (Activities like RCC, brickwork, plastering etc) got slowed down during April to Middle of June due to non-availability of sand/aggregates in U.P |
| Completion chart |
Project 19
Trauma Centre and Emergency Medical Block at Malda Medical College and Hospital at Malda under PMSSY Phase-3.
| Zone | EZ I |
|---|---|
| Approved DPR cost(AA & ES) | 61.39(Amount in Rs crore ) |
| Approved contract value | 44.96 |
| Date of Award / Target date of completion | 17.12.2016 / 16.08.2018 |
| Date of completion as per current progress | 31.12.2018 |
| Status of work | The work is yet to start as site has not been made available by the hospital administration. |
| Amount allocated | 6.13(Amount in Rs crore ) |
| Hindrances | Site not clear. Nurses hostel existing on the site is being demolished by the college. |
| Completion chart |
Project 20
Up-gradation of B. S. Medical College, Bankura under PMSSY, Phase-III
| Zone | EZ III |
|---|---|
| Approved DPR cost(AA & ES) | 79.00(Amount in Rs crore ) |
| Approved contract value | 54.50 |
| Date of Award / Target date of completion | 05.08.2016 / 31.03.2018 |
| Date of completion as per current progress | 31.03.2018 |
| Status of work | Shuttering of 4th slab in progress. |
| Amount allocated | 41.00(Amount in Rs crore ) |
| Hindrances |
|
| Completion chart |
Project 21
Upgradation of Government Medical College & Hospital at Akola under PMSSY Phase-3.
| Zone | |
|---|---|
| Approved DPR cost(AA & ES) | 74.75(Amount in Rs crore ) |
| Approved contract value | 48.19 |
| Date of Award / Target date of completion | 10.09.2016 / 31.10.2019 |
| Date of completion as per current progress | 09.01.2018 |
| Status of work | Right block-1st floor slab & beam reinforcement placing in progress. Left block- 3rd floor columns in progress. AAC block masonry completed at GF. Work is 96% completed |
| Amount allocated | 48.00(Amount in Rs crore ) |
| Hindrances | 1st & 2nd Milestones shifted by 75 days. The agency agreed to cover up this delay of 75 days by the end of 3rd milestone. Hence the date target date is the same as the stipulated date of completion. |
| Completion chart |