Construction of Permanent Campus of Indian Institute of Management Amritsar Punjab

Construction of Permanent Campus of Indian Institute of Management Amritsar Punjab Phase-I (SH- Construction of Various Buildings including Civil, Electrical & Mechanical, Furniture and Horticulture Works/Services/Developments on Turnkey/EPC Basis)

Project Name : Construction of Permanent Campus of Indian Institute of Management Amritsar Punjab Phase-I (SH- Construction of Various Buildings including Civil, Electrical & Mechanical, Furniture and Horticulture Works/Services/Developments on Turnkey/EPC Basis)

NIL
img

28711 Lakh

Project Budget

img

17 Jul 2020

Start Date

img

16 May 2022

Completion Date

img

Punjab

Location

Project Team / Contact Us

S.No. Name(Mr/Mrs) Designation Office Address Office Number Mobile Number Email ID
1 Gurbax Singh CEcumED IIT Project Ropar Birla Farm CPWD Ropar Punjab rprcomiitpz@cpwd.gov.in
2 Nitin Kohli EESMcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab asreesm4-iim@cpwd.gov.in
3 Roop Lal EESMcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab amt-ee-iimapd@cpwd.gov.in
4 Pratish Singhal EESMelectrical IIT Project Ropar Birla Farm CPWD Ropar Punjab ee.iitrped.cpwd@gov.in
5 Harjinder Singh AEEcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab amt-aee-iimapc@cpwd.gov.in
6 Jasvinder Singh AEcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab jasvinder.singh66@gov.in
7 Brahm Kumar AEcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab brahm.kumar@gov.in
8 Manjeet Singh AEcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab manjeet.s64@gov.in
9 Deepankar Koli AEcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab deepankar.koli1979@gov.in
10 Sumit Kumar Arya AEcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab sumit.arya@gov.in
11 Nand Kishor AEcivil IIT Project Ropar Birla Farm CPWD Ropar Punjab

Smart Features

S.No. Smart Features Images
1

Green Building certification of 4 Star GRIHA Green rating for Integrated Habitat Assessment rating

2

New Technology Structure with Monolithic RCC construction using Aluminum shuttering for high rise buildings Hostel block Associate Professor Residences and Non Teaching Staff Residences

3

Centralized Air Conditioning for all buildings except residences

4

BMS

5

Use of AAC blocks

6

Solar water heaters

7

Energy efficient motors in pumps and energy efficient chillers for HVAC

8

Minimizing dust pollution by barricading the construction area and dust curtains

9

Road network shall be flexible pavement with footpath and walkways having CC kerb stone

10

Sewage Treatment Plant of 200KLD for recycling of waste water

11

Rain water harvesting and water efficient fitting for water consumption

12

100 percent Low discharged plumbing fixtures

13

PUF insulation on Terrace

14

Solar Heat reflective Tiles on terrace

15

Double Glazed unit

16

Zero discharge campus 100 percent utilization of waste water after treatment

17

No wastage of Rain Water with the Rain Water Harvesting wall

18

Low VOC Paint

19

Cavity Walls

20

Use of Self Compacting concrete

21

100 percent usage PPC Cement

Implementation Strategy

S.No. Description Images
1

Through open tendering in EPC mode

Name of contractor  M/s NKG Infrastructure Ltd

Tender Cost Rupees 2871133398

Lessons Learnt / Take Aways

S.No. Description Images
1

Experience of the contractor in Alumiium Shuttering work should be considered